General informationClientChevron Australia ProjectGorgon Stage Two Year2020-21 LocationNorth West Shelf, Western Australia VesselsAudacia, Fortitude Max. water depth1,325 m
Scope of workInstallation of production flowlines, mono-ethylene glycol (MEG) pipelines and utility pipelines totalling 47 km, and pipeline end terminations (12)Supply, fabrication and installation of anti-burial mattresses, buckle initiator sleepers and active pipe supportsSpan correction, and conducting flooding, cleaning, gauging and hydro testing (FCGT) of all pipelines
Project specialsDeep-water installation close to live assetsPipeline head removal using laydown head removal framesProduction flowlines cladded with corrosion resistant alloyComplex FCGT campaign with specialised flooding mediumsFirst job in Australia for Fortitude