27 August 2019

New extensive video of the Brent Bravo removal

Watch the new extensive project movie of Pioneering Spirit  removing the Brent Bravo topsides on 18 June 2019.

Allseas’ record-breaking heavy lift and pipelay vessel Pioneering Spirit  has safely completed the single-piece removal of the 25,000 t Brent Bravo topsides from the North Sea. Completed early Tuesday morning, the operation took approximately 4 hours, from positioning the vessel around the platform to the moment of the lift. The actual “fast lift” of the topsides took only 9 seconds.
Read more about the Brent Bravo removal project.