Sur de Texas

General information

Client Infraestructura Marina del Golfo (TransCanada) 
Project Sur de Texas 
Year 2017 
Location Gulf of Mexico 
Vessels Solitaire, Tog Mor 
Max. water depth 100 m

Scope of work

  • Engineering and installation of 685-km, 42-inch pipeline
  • Dual 42-inch pipe pull-out at Altamira and direct 42-inch pipe push-out at Tuxpan
  • 4 x 42-inch pipe above water tie-ins
  • 545 km post-lay trenching
  • Pre-commissioning and testing of the system