Karish Development

General information

ClientEnergean Oil & Gas (via TechnipFMC) 
ProjectKarish Development 
Year2020 
LocationEast Mediterranean (Israel) 
VesselsSolitaire 
Max. water depth1750 m

Scope of work

  • Installation of 90-km gas export pipeline (starting as 30-inch and reducing to 24-inch after 12 km)
  • 2.5 km pull-in (partly through a casing), 2 dummy spools (for future manifold tie-in) and a 100 t PLET
  • Transportation of some 7500 pipe joints from Cyprus to installation vessel